Export packaging fails when it is treated as a crate design rather than a preservation plan. A motor may pass through truck vibration, port storage, salt-laden air, lifting transfers and months in an unconditioned warehouse before installation. The packing method has to address that complete route.

Write the logistics profile first

The supplier cannot select an appropriate barrier from the destination country alone. Provide a route profile with:

  • transport modes and expected trans-shipments;
  • lifting and forklift access points;
  • maximum packed dimensions and mass restrictions;
  • indoor, covered-outdoor or open storage;
  • expected time from packing to commissioning;
  • temperature and humidity range;
  • salt spray, dust, rain and flooding exposure; and
  • customs inspection or crate-opening requirements.

If the route is unknown, state a conservative design basis and list it on the packing drawing. A hidden assumption is difficult to recover after condensation or bearing damage is found.

Protect different failure paths separately

Risk Typical control to specify Receipt evidence
Bearing damage from shock or vibration Rotor restraint where required, resilient support, handling marks and indicators Lock condition, indicator record and free-rotation check after authorised removal
Corrosion on machined surfaces Compatible temporary coating and sealed protection Coating intact on shaft extension, flange and exposed fasteners
Condensation in windings or terminal boxes Moisture barrier, desiccant/indicator or controlled ventilation, heaters if designed for storage use Humidity indicator, heater record and insulation test before energisation
Water or dust entry Sealed openings, covers and weather-resistant outer package Covers and seals intact; no water marks or debris
Lost identity or accessories Weatherproof external marks and protected document/accessory list Model, serial number, package number and accessory count reconcile

ABB’s manual for induction motors and generators describes transport locks for some machines, corrosion protection for machined surfaces, drained sleeve-bearing oil systems and seaworthy packing against water, salt spray, moisture, rust and vibration. Those are machine-specific controls; the packing drawing must show which ones apply to the ordered motor.

The storage plan starts at receipt

Receipt inspection should happen before the carrier leaves when practical. Photograph all sides of the package, indicators and any damaged area. If a barrier bag must be opened, define how it will be resealed and how desiccant will be replaced.

Move the motor to the specified environment and start a storage log. A useful log records date, package condition, humidity indication, space-heater status, corrosion check, bearing-preservation action and the person performing it.

Do not use a generic shaft-rotation interval. ABB instructs users of certain rolling-bearing machines to turn the rotor 10 revolutions every three months, while Siemens instructions for other products may state a different interval. The correct action is the one in the exact motor manual, and any transport lock must be handled correctly. See ABB’s storage instructions for rolling bearings.

Before commissioning

The storage release should reconcile the motor, documents and preservation history. At minimum:

  1. inspect for corrosion, water entry, damaged terminals and loose internal items;
  2. remove transport restraints only according to the manufacturer’s procedure;
  3. confirm lubricant condition and any renewal requirement;
  4. verify free rotation where the manual permits it;
  5. measure winding insulation using the approved method and record winding temperature;
  6. check accessories, heaters and temperature sensors; and
  7. restore drains, plugs and covers to their operating configuration.

An insulation reading does not erase evidence of water exposure, and a clean exterior does not prove that a bearing survived transport shock. Both electrical and mechanical checks are needed.

Purchase-order wording that prevents ambiguity

State the preservation duration from factory packing, not from arrival. Require a packing drawing, centre-of-gravity and lift marks, package mass, applied preservation materials, transport-lock instructions, storage maintenance schedule and recommissioning checklist. Require visible marking of any action that can damage the motor if missed.

Release rule

Approve the package when every expected hazard has a control and every control has a receipt or storage check. If the route or storage time changes, revise the preservation plan instead of assuming the original crate remains adequate.