Motor packaging is part of equipment preservation. A heavy machine can arrive with no visible damage and still have moisture inside the barrier, bearing grease migration, corrosion, insulation contamination or a displaced shaft restraint. The RFQ should therefore describe the route, climate, storage duration and unpacking decision rather than relying on the phrase “export seaworthy packing.”
Applicability boundary for packaging requirements
Use this guide for low-voltage, high-voltage, permanent-magnet and explosion-proof motors shipped by sea, road, rail or air. It applies to new equipment, spare motors and repaired machines waiting for installation. It does not prescribe a single crate material or a universal desiccant quantity. The supplier must size the packaging from the motor mass, surfaces, route, climate, transit time and storage plan.
Freeze the route from factory to final store, including trans-shipment, port dwell, customs delay, outdoor exposure, warehouse humidity and expected unpacking date. A package designed for a five-day inland journey may be inadequate for a humid sea route followed by six months in an unconditioned store.
Transport and moisture RFQ matrix
Place these requirements in the inquiry and ask the supplier to mark each one as included, excluded or requiring clarification.
| Hazard | RFQ control | Record at shipment or receipt | Acceptance response |
|---|---|---|---|
| Rain and sea spray | Continuous moisture barrier with sealed joints | Barrier photographs and seal list | Hold and inspect if punctured |
| Humidity ingress | Desiccant sized for volume and duration | Desiccant batch and indicator record | Replace and re-preserve |
| Condensation | Venting or thermal design for temperature cycling | Humidity indicator and climate log | Moisture assessment before energising |
| Shock and impact | Base restraint, lifting points and shock indicator | Indicator status and case inspection | Engineering review of exceeded event |
| Vibration | Bracing for rotor, bearings and accessories | Packing drawing and restraint check | Recheck shaft and bearing condition |
| Corrosion | VCI, coating, plugs and protected machined surfaces | Product batch and application record | Clean, recoat or repair as approved |
| Long storage | Periodic inspection and re-preservation instruction | Store inspection log | Extend or release preservation |
| Forklift and lifting | Marked centre of gravity and handling points | Handling photographs and labels | Stop if case is lifted incorrectly |
| Unpacking | Controlled sequence with inspection hold point | Receipt report and photographs | Release only after closure |
The matrix makes packaging a verifiable deliverable rather than a decorative part of the commercial offer.
Common packaging mistakes
The first mistake is specifying a case but not a barrier. A solid wooden box can trap humid air around cold metal. The second is adding desiccant without defining the package volume, barrier integrity or replacement interval. The third is locking the shaft without documenting how the restraint is removed. A fourth is allowing the supplier to place heaters, RTDs or terminal accessories in the same package without a moisture and impact plan.
Do not treat a green humidity indicator as proof that insulation is ready for energisation. Do not use VCI paper on surfaces or materials that the manufacturer excludes. Do not remove preservation during customs inspection without a controlled resealing method. If a case is opened, the event, person, time, new seal and new desiccant must be recorded.
Decision steps before issuing the RFQ
- Map the route, climate, handling points, storage location and intended unpacking date.
- Identify motor mass, centre of gravity, rotor restraint, bearing type and vulnerable surfaces.
- Define moisture, corrosion, shock, vibration and long-storage controls.
- Ask suppliers to submit a packaging drawing and a packing-material schedule.
- Review indicator, desiccant and preservation evidence against the duration case.
- Define the receipt inspection hold point and release-to-service checks.
- Record exclusions, extensions and re-preservation responsibilities in the purchase order.
Supplier data to request
Request case dimensions and mass, barrier construction, seal method, desiccant type and quantity basis, humidity-indicator location, VCI product and batch, shaft-lock design, bearing preservation, surface-protection plan, lifting and forklift marks, centre-of-gravity drawing, shock indicator specification and storage-inspection interval.
Ask for photographs before closing the case and a packing list tied to the motor serial number. Require the supplier to state how the package may be opened for inspection and how it must be resealed. For long storage, request a calendar with inspection, shaft rotation, heater checks, insulation tests and preservation renewal tasks.
Receipt inspection and release boundary
At receipt, photograph the case before unloading. Check impact indicators, water marks, broken seals, case distortion, lifting damage and label legibility. Do not open a case in rain or high humidity unless the preservation procedure allows it. After opening, record the indicator state, desiccant condition, visible corrosion, shaft restraint, bearing seals, terminal-box condition and any foreign material.
Release to installation only after the receipt record is complete and the approved motor-preservation procedure has been followed. Insulation resistance, winding temperature, bearing condition and space-heater checks should be performed under the responsible engineer’s limits. If moisture is found, hold the motor and document drying, retesting and the decision authority.
Final RFQ rule
The best packaging requirement is one that explains what will be protected, for how long, against which route hazard and with which receipt evidence. A supplier who can show the design basis, inspection records and re-preservation method has answered the real risk; a supplier who only writes “seaworthy packing” has not.
Route-specific design review
Review the packaging against the worst credible route segment, not the average journey. A motor that travels through a hot port, a cold inland warehouse and a humid final store may experience several condensation cycles. Ask the supplier to show how the barrier, desiccant, indicator and venting arrangement behave when the case temperature changes. If the case will be lifted more than once, check that the restraint and centre-of-gravity marks remain usable after a damaged or replaced outer panel.
For heavy rotors, require a clear distinction between shipping locks and operating restraints. The packing list should show the number, location, removal method and temporary storage of each lock. A missing lock can permit impact during transport; a lock left installed can damage the shaft or bearing at startup. Include a removal sign-off in the receipt inspection rather than leaving it as an informal instruction on the case.
Where a motor contains heaters, RTDs, brakes or terminal accessories, protect their leads and connectors from compression and condensation. Request a component-level packing sketch that shows separation from loose desiccant and corrosion-inhibitor materials. The supplier should state which parts may be opened for customs inspection and how the barrier is restored without changing the preservation period.
The RFQ should also define who pays for re-preservation when the route or storage duration changes. If a shipment is delayed, the logistics owner should notify engineering before the original preservation date expires. A clear extension procedure is cheaper than discovering rust or low insulation resistance when the motor is finally uncrated.
Include a simple exception form for damaged cases, wet barriers, missing labels or exceeded shock indicators. The form should capture the package serial, location, weather, photographs, temporary protection, engineering disposition and next inspection date. This makes the decision portable when a carrier, port operator and plant warehouse each hold a different part of the shipment record.
For motors with space heaters or electronic accessories, state the maximum storage temperature and whether the package may be connected to temporary power while stored. If temporary power is allowed, define the inspection and isolation method so a heater cannot be energised with an open terminal box or a wet package. Also identify the point at which insulation testing is required before the motor may be rotated, coupled or connected to the plant supply. These details turn a preservation instruction into a controlled release sequence.