Alignment is often treated as the final adjustment before a motor starts. In reality, the result depends on the base, soft foot, coupling, piping, thermal condition, bolt torque and measurement method. A perfect-looking laser report can become invalid when a foot lifts during tightening or a pipe pulls the driven machine. The acceptance record must therefore show the installation state in which the motor will operate.

Applicability and boundary

This method applies to horizontal and vertical motor-driven trains with flexible or rigid couplings, including pumps, fans, compressors, conveyors and gearboxes. It is suitable for new installation, replacement and post-maintenance return to service. It does not prescribe a universal offset or angular limit; use the coupling maker, motor supplier, driven-machine instruction and project standard for the actual speed and duty.

Freeze motor and driven-machine identity, shaft dimensions, coupling type, base arrangement, bearing arrangement, thermal-growth target, piping state and operating speed. If a motor is mounted on rails or slide bases, include the travel and locking method. If a vertical machine has thrust or pipe-load constraints, define them separately from the alignment reading.

Alignment and soft-foot acceptance matrix

Installation state Required check Evidence Hold point
Base before motor placement Flatness, anchor condition and grout or soleplate state Survey and photographs Stop if base is unstable
Motor placed, bolts loose Initial shaft and foot condition Foot map and preliminary readings Correct gross condition
Soft-foot check Foot lift at each bolt under controlled tightening Feeler or indicator record Shim or correct before alignment
Coupling installed Face, rim, axial gap and key condition Coupling inspection and dimensions Hold for wrong fit or damage
Cold alignment Horizontal and vertical offsets at known temperature Laser or dial report Adjust to approved target
Connected piping Strain and alignment change after connection Pipe-strain readings and repeat alignment Release only after closure
Final torque Bolt torque, shim pack and locking state Torque sheet and shim record Recheck if torque changes result
Warm or operating condition Thermal target and baseline vibration Startup record and trend Hold for unexplained movement

Common installation mistakes

The first mistake is aligning before correcting soft foot. The second is using a laser target without confirming the correct coupling dimensions, rotation direction and thermal-growth sign. A third is accepting a base that is flat at one point but unsupported under the feet. Another error is connecting piping or a guard after the final measurement and assuming the result remains unchanged.

Do not stack an uncontrolled pile of thin shims. Record shim material, thickness, location and contact. Do not loosen all hold-down bolts at once on a heavy motor. Do not use a cold target copied from another train when the speed, shaft span or operating temperature differs. If a reading changes after torque, the torque state is part of the cause and must remain in the evidence.

Decision steps for commissioning

  1. Confirm the machine boundary, coupling and installation instructions.
  2. Survey the foundation and establish a repeatable measurement reference.
  3. Check soft foot before making alignment adjustments.
  4. Verify coupling fit, gap, key, guard clearance and axial movement.
  5. Calculate thermal target from approved sources and state its sign.
  6. Align in horizontal and vertical planes, then repeat after final torque.
  7. Recheck after piping, guards and connected auxiliaries reach the agreed state.
  8. Start under a controlled procedure and compare vibration, temperature and current with the baseline.

Supplier and RFQ data request

Request shaft and coupling drawings, allowable radial and angular offsets, axial float, thermal-growth values, foundation flatness and grout requirements, hold-down bolt size and torque, shim limits, soft-foot acceptance method and alignment report template. Ask the supplier to identify whether the target is based on coupling centre, shaft centreline or machine feet.

For pump or compressor installations, request allowable nozzle loads and the pipe-strain acceptance method. For a VFD system, request the startup speed range and any resonance or minimum-speed restrictions that affect the warm alignment check. Ask for the recommended instrument resolution and calibration interval when the project requires witnessed acceptance.

Handling an alignment dispute

Preserve the first result, then identify the state that changed: bolt torque, temperature, coupling assembly, piping, foundation support or instrument setup. Do not average conflicting readings. Repeat from the same reference and record the changed condition. If the machine needs a temporary shim or pipe support, record its design intent, owner and removal or permanent-fix date.

The final acceptance should state the machine temperature, speed, load, measurement method, offsets, angular values, soft-foot result, torque state, pipe-strain result and startup observations. A report that lists only a green “pass” box is not enough to support later troubleshooting.

Final acceptance rule

Accept the installation when the base is stable, soft foot is corrected, coupling and thermal targets are documented, final torque does not invalidate the readings, connected systems do not introduce unacceptable strain and the startup baseline is recorded. If any boundary remains unknown, hold the machine or define a controlled temporary condition rather than treating alignment as complete.

Measurement technique and repeatability

Before taking readings, confirm that the instrument brackets are rigid, the shafts can rotate through the required positions and the reference marks are repeatable. Record the shaft diameter, coupling span, detector resolution and the number of measurement positions. A laser report without these inputs can be difficult to audit when another technician obtains a different result.

Check for thermal growth in the direction that the motor actually moves. A target calculated with the wrong sign can deliberately create a misalignment at operating temperature. If the supplier provides a thermal value, record its source, speed, bearing arrangement and reference temperature. If the driven equipment supplier provides a different value, stop and resolve the interface instead of averaging two targets.

Soft foot should be checked with the machine in the same support and bolt condition used for alignment. Loosen one foot at a time, observe movement and record the correction. After shimming, torque the bolt and repeat the check; a correction that passes with loose bolts but fails after torque is not closed. Keep the final shim map with the alignment report so future maintenance can restore the same support state.

After coupling and piping are complete, take a final “as-operated installation” record before the first full-load run. Compare current, bearing temperature and vibration with the cold alignment baseline. If the machine moves as it warms, record the direction and magnitude and compare it with the target. That trend is often more useful than a single green alignment printout because it shows whether the installation behaves as designed.

Acceptance hold points

Set explicit hold points at foundation acceptance, soft-foot closure, coupling installation, cold alignment, pipe-strain check and warm baseline. Only the named responsible engineer should release a hold point. If a contractor changes a shim pack, coupling, pipe support or bolt torque after release, reopen the affected point and record the reason. This prevents a late field adjustment from silently invalidating the original acceptance.

Keep the final report understandable to the maintenance team who will work on the train later. Include the machine tag, shaft rotation direction, coupling type, target values, actual readings, shim map, torque values, instrument identification and photos of reference marks. A compact record is more useful than a large export whose critical settings cannot be found during the next outage.

Going deeper — installation acceptance