Record the motor package as delivered before opening it or making avoidable changes to its condition. Use the evidence map below to organise photographs, shipping records and exceptions, then agree a controlled unpacking plan for any damaged or suspect package.

For a project-specific enquiry, send packing list, delivery photographs and recorded exceptions. Keep original delivery photographs and distinguish observations made on arrival from changes made during unloading or opening; include the package and motor identifiers.

A disciplined inspection takes little time compared with a disputed claim or damaged motor. Its purpose is to identify the shipment, make handling safe, preserve external evidence and decide whether normal unloading, controlled opening or quarantine is appropriate.

Applicability boundary before unpacking

Use this method for crated, skidded or covered industrial motors and motor auxiliaries delivered by road, rail, sea or air. It applies at ports, project laydown areas, warehouses and final sites, including transfers between contractors.

The process does not replace a detailed internal receiving inspection. External condition cannot prove that bearings, windings, shaft, fan or accessories are undamaged. Nor does a damaged crate automatically establish carrier liability. Contract, custody, insurance and investigation evidence govern any claim.

Safety takes priority over photography. Do not enter an unstable cargo unit, stand under suspended loads or approach shifted cargo merely to complete a checklist. Secure the area and use competent logistics personnel when structural damage, leakage or load movement is suspected.

Pre-unpacking evidence map

Assign photograph numbers and observations to the motor tag or shipment line. Use an orientation convention such as door side, opposite side, drive end and non-drive end.

Observation point What to record before movement Evidence format Decision or notification
Transport unit identity Container, trailer or vehicle number Wide photograph and delivery document Confirm expected shipment
Seal identity and state Number, intact/broken/missing condition Close-up before removal Notify discrepancy before opening
Cargo position Orientation, shift, lean and restraints visible from safe point Wide photographs Obtain unloading plan if shifted
Crate identity Tag, package number, gross mass and handling marks Label photograph Reconcile packing list
All external faces Holes, crushing, abrasion, stains and open joints Systematic face photographs Mark damage locations
Base and skid Broken members, fork damage and fastener condition Low-angle photographs where safe Review lifting method
Roof and cover Ponding, puncture and displaced weatherproofing Safe external view Protect from further exposure
Shock indicator Identifier, state and location Context plus close-up Preserve and escalate if triggered
Tilt indicator Identifier, state and location Context plus close-up Verify handling history
Moisture evidence Water marks, condensation, wet timber or torn barrier Photographs and environmental note Plan controlled opening/drying assessment
External corrosion or leakage Location, colour and extent Scaled photograph Quarantine and identify source
Accessory packages Count, condition and attachment Packing-list reference Prevent separation or loss
Delivery condition note Carrier remarks and receiver observations Signed document Record reservations before acceptance where allowed
Time and custody Arrival, inspection and handover times Timestamped log Start notice clock

Do not rely only on close-ups. Every detailed image needs a context image so another reviewer can locate the defect. Keep original files and metadata according to project rules.

Decision steps at the delivery point

  1. Review expected package count, mass, lifting plan, carrier details and notice requirements before arrival.
  2. Establish a safe inspection zone and identify the authorised receiver.
  3. Confirm transport-unit and seal identity before breaking the seal.
  4. Photograph delivered position, restraint condition and package orientation from safe viewpoints.
  5. Reconcile crate markings and package count with shipping documents.
  6. Inspect every accessible face, skid, cover and handling indicator.
  7. Record weather and visible moisture conditions where relevant.
  8. Classify the package for normal unloading, controlled unloading or quarantine.
  9. Enter specific reservations on the delivery record where contract and local process require them.
  10. Notify carrier, supplier, insurer or contract owner within the applicable route and timeframe.
  11. Develop a controlled-opening plan for any suspect package and invite witnesses where required.
  12. Transfer custody with condition, storage destination and next inspection owner recorded.

The receiver should know who can stop unloading. Schedule pressure is not a reason to move a crate whose lifting points, base or centre-of-gravity control may be compromised.

Common errors that destroy useful evidence

Taking the first photograph after moving the crate. The delivered position and restraint arrangement are then unavailable for reconstruction.

Signing “received in good condition” from a package count. Quantity and condition are different observations. Use the wording and reservation process authorised by the contract owner.

Resetting or discarding handling indicators. A triggered device does not prove damage, but destroying it removes evidence. Record identifier and state, then preserve it.

Photographing damage without identity. A close-up of cracked timber cannot support a specific motor if the image lacks package context, date or tag linkage.

Opening a wet package in rain. The team can introduce more water and confuse the damage boundary. Move or shelter it under an approved plan without losing external evidence.

Assuming intact packaging means intact equipment. Loads can experience shock, vibration or internal restraint failure without obvious exterior damage. Continue with the specified internal inspection.

Diagnosing from an indicator alone. A shock or tilt device records a threshold event under its own installation and specification. Engineering must decide the appropriate internal checks.

Splitting loose accessory crates from the main record. Lost coolers, sensors, glands or tools can delay commissioning even when the motor itself is sound.

Supplier and RFQ requirements for receiving control

The RFQ should request a packing specification appropriate to route, lifting method, climate and planned storage. Require package numbers, motor tags, gross and net mass, dimensions, centre-of-gravity marking, lifting points, sling restrictions and stacking limitations where relevant. The shipping drawing should show shaft restraints, internal supports and loose-shipped auxiliaries.

Ask for a packing list detailed enough to reconcile each crate and accessory. Define any required shock, tilt, humidity or tamper indicators, including identifier, location and interpretation instructions. Do not add indicators without defining who reviews them and what a triggered state requires.

Request instructions for safe opening, preservation, storage and re-closing after inspection. Clarify supplier response and witness requirements when external damage is found. Commercial documents should separately define custody transfer, notice method, claim evidence and insurance responsibilities.

Controlled opening after an external exception

When external evidence indicates possible damage, write an opening plan before cutting barriers or removing restraints. Identify witnesses, safe lifting, photograph sequence, moisture protection and components requiring inspection. Retain removed packaging sections, indicators or restraints where they may support investigation.

Open in stages. Record the condition immediately inside the outer layer, then barriers, blocking and the motor. Water paths, rub marks and shifted supports can show how an event reached the equipment. Avoid cleaning until observations are complete.

The internal scope should follow the event. A triggered tilt indicator may justify checks of restraints, shaft, bearings, lubrication and mounted auxiliaries; water entry may justify insulation, terminal, heater, sensor and corrosion assessment. The responsible engineer should define checks rather than applying a generic “looks fine” release.

Receiving acceptance and claim-ready closure

Close the pre-unpacking inspection when shipment identity and count are reconciled; all accessible package surfaces and indicators are documented; delivery reservations and notifications are issued as required; safe unloading disposition is approved; and custody transfers to a named storage or opening owner.

A suspect package remains under controlled status until internal inspection and technical disposition are complete. Do not let warehouse booking convert quarantine into acceptance. Link every exception to an NCR, damage report or claim reference.

The final evidence set should include original photographs, time and location, delivery documents, seal record, package map, indicator details, weather observation, witness names, notifications and subsequent opening report. This protects both sides: genuine transport damage can be investigated, while unrelated later damage is less likely to be assigned to delivery without evidence.