A terminal-box side and cable-entry direction affect bend radius, gland arrangement, phase sequence, drainage and maintenance access. A catalogue position is not approval for the actual cable route.

Treat terminal-box orientation as an installation interface

Overlay the motor drawing with the cable tray and foundation layout. Include power, earth, heater, RTD and encoder entries. Rotation of a box may be restricted by internal leads, enclosure certification or drain orientation.

Interface check

Item Engineering purpose Review action
Entry direction Cable approach and bend Avoid side load on terminals
Gland plate Hole size and material Match cable and sealing system
Internal links Phase arrangement Confirm connection diagram
Working space Cover and tool clearance Permit safe termination

Evidence required before approval

Inspect gland torque, cable support, creepage clearances, phase markings and protective-earth connection before energisation. Approve only from a controlled drawing showing orientation and every entry.

Retain the equipment revision and test record. Name the reviewer. Keep open assumptions visible.

Commissioning decision

Never approve a copied setting. Confirm interface compatibility and operating limits. Exercise the intended response during a functional test.